Home / Calculators / Slab Calculator

Concrete Slab Calculator

Concrete, steel and material quantities for an RCC slab — by dimensions and grade.

Slab inputs

Materials for this slab

Live scaled view — proportions update as you type
Dry volume: 3.375 × 1.54 = 5.198 i Concrete shrinks when wet, so the dry materials needed are the wet volume × the 1.54 bulking factor (standard site practice) before splitting by grade. See the method →
Concrete volume
3.375
Cement
28 bags
Sand
1.4
Aggregate
2.8
Steel (est.)
270 kg

Estimate using dry factor 1.54 (mortar 1.33), 50 kg bags, 5% wastage. Verify with a structural engineer.

Add elements in the BOQ →

How the slab calculation works

Slab concrete volume is simply length × width × thickness. The material split then follows the chosen grade and the 1.54 dry-volume factor — the same method as the main calculator, shown in full on the method page. For an M20 slab, every cubic metre of concrete works out to roughly eight 50 kg cement bags, 0.42 m³ of sand and 0.84 m³ of aggregate, with about 200 litres of water at a 0.5 water-cement ratio.

The steel figure is an estimate using a typical reinforcement density of about 80 kg per cubic metre for slabs. Actual steel depends on span, loading, support conditions and your structural design — treat it as a planning number for budgeting and ordering, not a substitute for a detailed bar bending schedule. When you need real cut lengths and bar-wise weights, use the bar bending schedule calculator instead.

One-way vs two-way slabs

A one-way slab spans in a single direction and is common for verandahs, walkways and rooms where one pair of sides is much longer than the other (a length-to-breadth ratio above two). A two-way slab spans in both directions and suits roughly square rooms, distributing load more efficiently and usually needing slightly less concrete depth for the same span. The concrete volume from this calculator is the same either way — what changes is the reinforcement layout, which is why the steel figure here is only a guide.

Typical slab thicknesses

  • Residential floor slab: 100–150 mm
  • Roof slab: 100–125 mm
  • Heavily loaded or longer spans: 150 mm and above (engineer-designed)
  • Thin exterior paving / sunshade: 75–100 mm

Tips for ordering

Always add a wastage allowance — this tool uses 5% on cement by default, which covers normal site loss during mixing and placing. Order aggregate and sand in brass (100 cft) if your supplier quotes that way; the other calculators and the BOQ let you switch units freely. For a continuous pour, having materials staged before you start avoids cold joints in the slab.

Need a full project, not just one slab? Add this slab along with beams, columns and footings in the BOQ estimator for a single costed bill of quantities with city rates and PDF/Excel export.
Questions

Slab Calculator — common questions

How much concrete do I need for a slab? +

Multiply the slab length, width and thickness (all in metres) to get the volume in cubic metres. For example, a 6 × 4.5 m slab at 125 mm thick is 6 × 4.5 × 0.125 = 3.375 m³. Enter your dimensions above and the calculator does this plus the cement, sand and aggregate split.

How many cement bags for a slab per m³? +

For an M20 slab, about 8 bags of 50 kg cement per cubic metre of concrete. M15 needs about 6.3 bags and M25 about 11. The calculator multiplies this by your slab volume and adds 5% wastage.

How much steel is needed in an RCC slab? +

As a planning estimate, residential slabs use roughly 80 kg of steel per cubic metre of concrete. The exact quantity depends on span, loading and design — use the bar bending schedule calculator for actual cut lengths and bar weights.

What grade of concrete is used for slabs? +

M20 is the most common grade for residential RCC slabs in India. Lower grades like M15 may be used for lightly loaded work, while M25 and above are used for heavier loads or longer spans, where a design mix is required.

We use cookies for analytics and ads. You can accept or decline non-essential cookies.